It may be hot, but down in the bowels of New York’s Pennsylvania Station it’s not really hell. Befitting the city’s well-known nickname, nobody here is sleeping at 2 AM – the renewal of Penn Station is a round-the-clock job. On the night of July 21st anticipation has been steadily building for the final placement of one of the many puzzle pieces of the station’s new track infrastructure. Switch 69B – everything is named numerically based on it’s position, with letters indicating the facing direction – is a massive piece of hardware that was assembled outside the station. In the cover of darkness it will be rolled in on its side, due to its width – when laid flat it is wide enough to foul the tracks on both sides.
With the last Amtrak train in the house at 1:40 AM, there’s a brief lull until the first morning departure at 3:25 AM. It’s in this window that the switch is laid flat just beyond the mouth of the Hudson tunnels and loaded onto Amtrak’s Portal Krane-1, which will bring the heavy piece to the correct spot and lower it into position on the already prepared track bed. PK-1, as it is abbreviated, is a Transformers-looking beast, with movable legs that allow it to “walk” the switch into position. It’s controlled by a complicated looking panel mounted to the body of the operator – I can only think of it as a joystick on steroids, and idly wonder if the fellow is any good at video games.
The night’s anticipation reaches its peak as PK-1, fully loaded, begins moving at 2:23 in the morning. When the vehicle reaches the right position next to the empty track bed, the operator controls PK-1’s legs to gradually shift the position of the switch. After several lateral shifting motions, the switch hovers in the appropriate spot just above the track bed. After trimming pieces of the already laid rail to accommodate it, the switch is finally lowered into position.
Concurrently, another team is hard at work on the other side of the station’s tracks. Most of the infrastructure for Track 10, including rails and ties, third rail and catenary have all been removed for a complete rebuild. Here, too, anticipation mounts for the arrival of the cement truck for the night’s pour. Word comes on the radio that the truck is on the move, enroute to the Empire tunnels, complete with police escort. Of course, Amtrak’s cement truck is a hi-rail vehicle; before long it will slowly roll down adjacent to Track 10, ready to encase the already installed wood ties.
Several photographers have gotten the chance to document the milestones happening in Penn Station, and I am lucky enough to be one of them. If you have seen Amtrak’s Media Images site or the new NYP Renewal Update video, you may have already seen some of my photos. Now, perhaps, they feel a little bit more real. If you’re like me, you may gain a new respect for the hardworking folks renewing the station, investing quite a bit of sweat in the wee hours of the morning.
Credit for all photos: Amtrak / Emily Moser. For more Amtrak images and videos, please visit the Amtrak Media website.
Excellent photos, getting out there in the wee hours of the morning I would bet they gained some respect for you as well!
Penn Station is not an easy place to do full scale trackwork,that was needed in this case.
Amtrak has done this under traffic,as Amtrak and LIRR run thru the night as well.
Do you know if Amtrak added some new switches off of “Track Two”(Empire Connector) to expand
the range of platform tracks that the Empire Service could use?
Interlocking “A” is maze of Puzzle switches(Double Slip switches) that is not easy to rebuild.
Truly amazing. Thanks so much for sharing. Hopefully some of the people who use Penn Station on a daily bases will look at these pictures and see how much hard work it takes to keep the clock ticking and to bring the station back to a good state of repair.